Watt/I-80 Transit Center Improvement Project
This construction project began July 2024 and includes a variety of improvements that will help create a safer, more accessible environment at one of the region’s largest transit hubs.

Latest Construction Updates
To access the temporary bus stop from the light rail station: Take the northbound stairs or elevator to Watt Avenue, turn left down Watt Avenue and follow the pedestrian detour signs to cross Watt Avenue at the crosswalk at Longview Drive. PLEASE NOTE: The pedestrian crossing across Watt Ave near the freeway on-ramp is now closed due to on-ramp construction. Please follow signs for your safety and cross at Longview Drive. The temporary bus stop is in front of the Sacramento Inn & Suites (formerly Red Roof Inn).
During this stage of construction, the southbound elevator and stairs are closed during construction. Riders can use the northbound elevator or stairs to get to the upper level. The northbound bus stop is not impacted at this time. This stage of construction is expected to last into May 2025.


About the Project
The Watt/I-80 Transit Center Improvement Project includes widening of the Watt Avenue Bridge, construction of an open-air stairwell linking Watt Avenue and the transit center, a new bus/pedestrian plaza, improvements to on-ramps, and upgrades to the portion of the transit center located beneath Watt Avenue. Collectively, these improvements will help attract more riders, accommodate additional bus service from other regional operators, and enhance the overall safety of the transit center.
Riders can expect temporary modifications in bus service during periods of construction, and drivers commuting to the transit center for bus or light rail service may also experience brief delays due to lane closures. SacRT will provide advance notice prior to any changes affecting bus service or access to the transit center.
Anticipated Construction Schedule
Subject to Change
December 3, 2024– May 2025
Construction on west side of Watt Ave, bus plaza (upper deck on Watt Avenue) and stairs. Southbound bus stops will be temporarily relocated.
January – April 2025
Construction to south on-ramp, lane and ramp closures expected.
May - July 2025
Watt Avenue median replacement, lane closures on Watt Avenue.
July 2025 - April 2026
Construction on east side of Watt Ave, bus plaza (upper deck on Watt Avenue) and stairs. Northbound bus stops will be temporarily relocated.
July – September 2025
Construction to north on-ramp, lane and ramp closures expected.
Mid 2026
The Watt I-80 Transit Center Improvement Project is expected to be completed.
Questions?
Project hotline: 916-566-5221